BESS Business Case: Controllable Value Creation for Your Municipal Utility

The most common question we hear from municipal utilities is not: “Is a battery storage system worthwhile?” It is: “How robust is the economic calculation—and what risk are we taking on?”

That is the crucial difference. Those who only ask about ROI think in point forecasts. Those who ask about predictability and risk corridors think like serious investors. It is precisely this second perspective that determines whether a BESS project passes the supervisory board—or fails because of it.

This article maps the three central economic levers of a battery storage system, ranks them by predictability, and shows which role model typically fits which municipal utility size and risk appetite.

What “controllable value creation” means for your municipal utility

“Controllable value creation” is not a marketing term—it refers to something precise: the part of the BESS business case that you can secure with your own data, independent of market price developments or regulatory changes.

What this means in concrete terms depends on your municipal utility size:

Small municipal utility (<€500 million annual revenue): Controllable value creation here primarily means grid relief and security of supply—levers that can be directly measured and planned using your own load profile. The critical question is not “What does FCR yield?” but rather: “How much demand charge reduction is realistic based on our load curve data?”

Medium-sized municipal utility (€500 million–€2 billion): Structured flexibility marketing comes into play here. A dedicated battery storage project with an external asset manager or optimizer enables systematic access to balancing energy markets (FCR, and depending on project setup, also aFRR)—with foreseeable revenue corridors based on historical market data.

Large utility (>€2 billion): Multi-asset strategy, portfolio optimization, in-house trading expertise. Controllable value creation here means hedging market risks strategically—for example, through a PSA (Power Sales Agreement) that secures a minimum revenue while selected marketing windows remain open for upside.

Common to all three: The most predictable lever is always the one based on your own data.

The three revenue levers—ranked by predictability

A battery storage system unlocks multiple revenue sources simultaneously. What matters is how reliably these sources can be calculated in advance.

Lever 1: Grid charge optimization—directly measurable

Demand charges account for 30–50% of grid charges at many municipal utilities. A battery storage system can shave load peaks and thereby reduce the demand component—based on your own load curve data. The savings potential can be precisely modeled before project start: not a scenario, not an assumption, but a calculation using your measured values.

This lever is not spectacular, but it is bankable—it can be documented with historical consumption data and creates the stable base revenue of any business case.

Lever 2: Balancing energy marketing—historically verifiable, but volatile

FCR (primary control reserve), and depending on project setup also aFRR, is the best-known revenue path for battery storage systems. Historical EPEX data allow modeling of revenue corridors—but: markets change. FCR prices have shifted significantly in recent years.

For a robust business case, this means: balancing energy markets belong in the sensitivity analysis, not in the base case. A stress test that still shows a positive net present value with a 30% revenue decline is more meaningful than an optimistic point forecast.

Lever 3: Avoided grid expansion—CAPEX comparison

Those who avoid or postpone grid expansion through a battery storage system achieve an indirect economic benefit: The CAPEX comparison between cable expansion and BESS investment often shows that the storage system is the more cost-effective solution—while additionally offering revenue potential that conventional grid expansion does not deliver.

This lever is the most difficult to monetize, but in many grid planning scenarios it is the strongest strategic argument before the supervisory board.

TCO predictability: Why the investment sum does not determine the business case

The most common question about the BESS business case is: “What does it cost?” The right question is: “What does it cost over the entire lifetime—and how do revenues and costs develop in different scenarios?”

Total Cost of Ownership (TCO) over 15 years includes:

  • CAPEX: Acquisition, installation, grid connection—the most visible, but not the sole decisive part
  • OPEX: Maintenance, insurance, monitoring, control center access, grid charges for internal consumption
  • Degradation: Capacity loss over the lifetime—typically 2–3% p.a. for LFP technology
  • Augmentation: When must capacity be retrofitted to maintain revenue profiles?
  • WACC: Financing costs and return requirements of your municipal utility

The core: Those who only optimize CAPEX are planning blind. An offer with a low list price but high OPEX costs and no clear augmentation option can be more expensive over 15 years than a higher initial investment with a transparent TCO structure.

For the financial buyer, this means: The business case must be presented as a sensitivity model. A tornado analysis covering CAPEX deviation, revenue decline, degradation rate, and WACC shows which assumptions most strongly influence the result. This is not uncertainty—this is methodological rigor.

Role models as an economic framework

How much risk your municipal utility wants and can bear determines the right business case more than the technology choice. Four role models are available:

Role ModelRisk ProfileRevenue PotentialInternal Effort
Contracting / JVVery lowLowMinimal
PSA (Power Sales Agreement)LowLow–MediumLow
Ownership + OptimizerMediumMedium–HighMedium
In-house OperationHighHighHigh

Contracting / JV: An external partner finances, builds, and operates—the municipal utility provides land and grid connection, receives usage rights or a stake. No CAPEX, minimal risk, but also little operational control.

PSA (Power Sales Agreement): A marketer takes over the storage project and guarantees the municipal utility a minimum revenue—the upside remains with the marketer. Maximum predictability with moderate returns.

Ownership + Optimizer: The municipal utility invests, an external asset manager handles ongoing marketing optimization. Full owner returns with limited internal operational effort.

In-house operation: The municipal utility assumes full responsibility—from investment to balancing energy marketing. Highest return potential, but also highest know-how and resource requirements.

Classification framework: Which model fits your municipal utility?

No two municipal utilities are alike. But three factors determine which role model typically fits best:

  1. Internal capacity: Do you have an in-house team that understands and can operate balancing energy markets?
  2. Grid connection status: Is a suitable grid connection realizable in the foreseeable future—or is the grid connection the actual bottleneck?
  3. Risk appetite: Which downside scenario is acceptable for your municipal utility without jeopardizing political and economic support?

Small municipal utility, low risk appetite: Contracting or PSA. No dedicated BESS team required—but full participation in the energy transition.

Medium-sized municipal utility, medium risk appetite: Ownership + Optimizer. Own asset, external knowledge provider, board resolution based on a clear TCO analysis.

Large utility, high risk appetite and in-house trading expertise: In-house operation with multi-asset strategy.

Important: The right entry point is not the “best” business case on paper—but the one that can actually be implemented in your organization and gains approval from internal boards.

Conclusion: Controllable value creation begins with your data

A BESS business case is not decided by the current market price for FCR—but by the quality of the data foundation, the choice of the right role model, and a TCO analysis that remains robust even under unfavorable scenarios.

The first step is always the same: your load profile. It shows which revenue lever has the greatest controllable potential for your specific consumption and feed-in behavior—and which role model fits accordingly.

Have your load profile analyzed—free and without obligation. Controllable value creation begins with data.

Request a load profile analysis now →

Battery storage in practice

Review of the panel discussion at the Wind Energy Days in Potsdam on November 13, 2025

The demand for battery storage is increasing rapidly. They are the central flexibility instrument in an energy system characterized by volatile generation. But how can storage projects in Germany be developed, approved, implemented and operated efficiently and economically? These were the central questions of the panel discussion at the Wind Energy Days in Potsdam – with experts from MVV Trading, JUWI and AXSOL.

The crowded room clearly showed: The market is looking for answers. And it needs them urgently.

The bottleneck: Grid connection as a critical success factor

One of the clearest statements of the panel: The biggest hurdle is and remains the grid operator.

While the approval authorities work cooperatively in many cases, grid connection processes are often slow or end with restrictions – especially for standalone storage systems that want to draw from and feed into the grid.

“The biggest hurdle in project development is clearly the grid connection. Co-location and hybrid approaches get connected to the grid much faster because they have the least affect on the grid.”

Felix Beyer (AXSOL GmbH)

Co-location and hybrid projects are clearly at an advantage.
They use existing grid infrastructure and reduce the grid load. Storage systems that exclusively feed in (green electricity storage) receive commitments comparatively faster, while gray electricity storage systems with bidirectional operation often encounter more skepticism.

Another trend:
Many grid operators are already demanding documentation ready for planning with the connection request – noise reports, lease agreements or layouts. This is intended to weed out non-viable projects early on. Good preparation significantly shortens the waiting time.

Location selection and dimensioning: The grid logic determines the project size

It became clear in the panel: Storage systems are not dimensioned theoretically, but grid-driven.

Overbuilding is allowed and makes sense.
Hybrid PV or wind farms can now be supplemented with battery capacities that are significantly higher than the nominal output of the generation plant. The reduced revenues due to grid bottlenecks are moderate:

  • PV + storage: about 6 to 8 percent
  • Wind + storage: about 10 to 17 percent


Profitability benchmarks from the panel:

  • Green electricity storage: approx. 100,000 euros per MW per year
  • Gray electricity storage: approx. 280,000 euros per MW per year
    (Basis: market years 2024/25)


This difference shows the value that storage systems with grid access can develop. However, this requires clean grid, measurement and control logic.

Approval: Complex, but manageable

Although the grid connection is the biggest hurdle, approvals are also challenging.
Relevant points:

  • Noise
  • Fire protection
  • Water law
  • Clearance distances
  • Access road and transport logistics


A possible future simplification could be the privileging of storage systems in the outer area discussed in the EnWG. If it were decided, it would be a real accelerator.

Realization: The actual construction phase is not the problem

A surprising point from the discussion:
The physical realization of a storage system is comparatively uncomplicated – especially compared to wind or PV plants.

The challenges lie elsewhere:

  • Delivery times for switchgear: 30 to 45 weeks
  • Container delivery time: 6 to 9 months
  • Transfer stations: biggest time waster
  • Total project duration: 18 to 24 months


The core message of the experts:
Early, parallel work is crucial. This includes discussions with the grid operator, marketer, EMS partner and testing organizations. Projects that involve all stakeholders late lose valuable months.

Integration: Why storage systems are not plug-and-play technology

It became clear in the discussion:
Storage systems differ fundamentally from other generation plants.
They are dynamic systems that react daily to price signals, grid requirements and control energy.

“Battery storage is not plug-and-play. Every co-location project is custom-made. The system only works reliably in the end if everyone involved is at the table early on.”

Vivien Klein-Campailla (MVV Trading GmbH)

Each project is a tailor-made manufacture:

  • Individual interfaces between BMS, PCS, EMS and EZA control
  • Different grid protection logics
  • Marketer requirements
  • Communication protocols
  • Controller architectures

Standardization is only emerging, it is not yet established on the market.

Therefore: Have marketers, EMS providers and EPC plan together early on.

AXSOL was able to provide insights in this area into how an integrated EMS (AXOS) can standardize interfaces and what role AI-based optimization (ADONYS) plays in operation.

Operation: Where profitability is gained or lost

Storage systems only generate revenue when they are available.
There is hardly any fault tolerance.

Target values in the market:
Availability between 95 and 97 percent.

This requires:

  • Spare parts availability within 24 hours
  • Structured escalation chains
  • Precise degradation management
  • Intelligent cycle strategy


It was emphasized that marketing and technical operation are closely interlinked.
A marketer can plan the best schedules – if a module fails, it needs quick communication and technical solutions.

“The revenues of a storage system only arise with high availability. Everything stands and falls with clean integration, fast response times and a well-thought-out service and fault management.”

Leon Jacob (AXSOL GmbH)

The discussion highlighted how important it is to plan cycles flexibly over the years.
A typical storage system today runs about two cycles per day, in extreme cases more.
But the decisive factor is the service life strategy, which must take manufacturer and marketer logic into account.

Marketing models: More variety, more options

The market is developing different remuneration models for storage operators.
Three models dominate:

  1. Profit Share / Fully Merchant
    Maximum opportunities, maximum risk.
  2. Profit Share with Minimum Guarantee (Floor)
    Stable planning with reduced volatility.
  3. Tolling model
    Fixed remuneration per MW per year, typical values: from around 118,000 euros.

This is particularly interesting for project developers with an investor background – plannability enables financing security.

Conclusion: Storage systems are system projects – not individual products

The central finding of the panel can be summarized in one sentence:

Successful storage projects only arise when technology, regulation, marketing and operation are considered together from the outset.

Battery storage systems are not isolated systems.
They are the interface between market, grid and generation.
Projects that take this perspective and support stakeholders early on will be realized faster, cause fewer risks and generate significantly higher revenues.

The industry is at the beginning of a massive scaling.

With the right setup, storage systems can play a key role in the future energy infrastructure – flexible, economical and safe.

Watch the complete discussion now and delve deeper into the current developments in the BESS market.